Extended-Dimension BIM-5D Applications in Engineering General Contracting Mode

Authors

  • Sitong Geng Architectural Engineering Institute, Kunming University of Science and Technology, Kunming, China

DOI:

https://doi.org/10.62051/9hfpkv37

Keywords:

Building information modeling; Engineering-procurement-construction projects; Green and intelligent construction.

Abstract

This study positions Building Information Modeling (BIM) - 5 Dimensional (5D), a BIM extension that combines a 3D model with time and cost dimensions, as the central digital support for an integrated management system across design, procurement, and construction in the face of ongoing cost escalation, schedule slippage, and phase discontinuities in Engineering-Procurement-Construction (EPC) projects. Three analytical axes are used in the discussion: (i) multi-actor and cross-disciplinary collaboration; (ii) execution that is focused on efficiency and precision; and (iii) intelligent and green construction. Research demonstrates that BIM-5D reduces design-site discrepancies, rework, and change orders by connecting design and construction through model-based review and virtual construction. EPC contractors may run a closed loop between plan and execution thanks to the framework's ability to tie component-level quantity take-offs to budgeting, synchronize them with 4D schedule visualization, and provide deviation notifications. Simulated energy use at the same time. Environmental monitoring and Internet of Things (IoT) field data facilitate scenario-based resource allocation and reduce material and carbon waste. All things considered, EPC projects that use BIM-5D can accelerate the transition to green and intelligent delivery by moving toward a data-driven, whole-process governance paradigm where quality, time, and cost are jointly managed and auditable.

Downloads

Download data is not yet available.

References

[1] Chen C, Lu S. Application of BIM-5D technology to whole-process construction management at Jiangnan Building. Fujian Architecture, 2020, 22(7): 114-115.

[2] Yang X J. Practice of BIM in large mixed-use complexes under the EPC model. Construction Economy, 2015, 16(4): 26-39.

[3] Wang J J, Li S N. Exploring a whole-process engineering consultancy model based on a BIM-5D digital project-management platform. China Engineering Consulting, 2022, 12(9): 94-98.

[4] Ye S F. Key applications of BIM-5D in refined control of airport construction projects. Intelligent Building & City Information, 2024.

[5] Wang J Y, Xu F. Cost-audit methods for residential construction projects based on BIM-5D. China Tendering, 2025, 10(7): 18-28.

[6] Liu X, Xie L L. Schedule-cost optimisation of construction projects based on BIM-4D/5D technologies. 2023.

[7] Wu B, Cai Y, Shi Y, Gao Z. Research on fine management of construction project based on BIM5D technology. IOP Conference Series: Earth and Environmental Science, 2020, 615(1): 120-134.

[8] Yang Y, Zhang T, Jiang R, et al. Research on the construction dynamic simulation and management using five-dimensional building information model. Smart Structures and Nondestructive Evaluation for Energy Systems 2023, 20(24): 130-183.

[9] Ren Y L. Application of intelligent construction technologies based on a BIM-5D platform. Green Construction & Intelligent Building, 2025, 32(8): 102-105.

[10] Wang X J, Jiang R G, Wu W P, Ma B, Zhu J W. Research and application of dynamic construction management based on BIM5D. IOP Conference Series: Earth and Environmental Science, 2019, 234: 012007.

Downloads

Published

30-12-2025

How to Cite

Geng, S. (2025). Extended-Dimension BIM-5D Applications in Engineering General Contracting Mode. Transactions on Engineering and Technology Research, 5, 206-212. https://doi.org/10.62051/9hfpkv37